Law & Regulation
Minnesota mechanic's lien and public bond deadlines: 45 days, 120 days and one year
Subcontractors must give owners a pre-lien notice within 45 days of first furnishing, then record a lien statement within 120 days of the last work. On public jobs, the payment bond notice is also due within 120 days.